Report No.: CCEER-99-2
Prestress Loss in Four Box Girder Bridges in Northern Nevada
Authors: N. Mangoba, M. Mayberry, and M. Saiidi
Date: March 1999
Sponsoring Agency: Nevada Department of Transportation (NDOT)
- Performing Organization:
- Department of Civil Engineering/258
- University of Nevada, Reno
- Reno, NV 89557
- Abstract:
- Four new post-tensioned, box girder bridges in Northern Nevada were instrumented during
construction to collect data on the possible adverse effects of high variation in relative
humidity (RH) and temperature on prestress losses. The bridges were monitored at short
intervals during the first month after stressing and in two-month intervals afterwards.
For each bridge, the measured data consisted of concrete surface strains on two girders,
creep strains on concrete cylinders at the bridge sites, shrinkage strains on cylinders at
the site and at the laboratory, and deflection of the midspan relative to the ends of the
structures. The actual time-dependent prestress losses due to creep and shrinkage were
calculated from the measured strain data. The measured losses were compared to two current
loss prediction methods: the AASHTO lump-sum estimate of prestress losses and the
time-step method of determining losses by Naaman. To determine the effects of changes in
RH on the losses, the climatic data of the area were incorporated into the calculated
losses.
- The losses predicted by AASHTO for the two-span bridges were within 7 percent of the
measured data (extrapolated). For South Meadows, AASHTO underestimated the losses by 7
percent, while for Mount Rose, AASHTO overestimated the losses by 7 percent. The single
span bridges studied exhibited a greater variation between the measured data and the
AASHTO predicted values. Lifetime creep and shrinkage losses were overestimated by AASHTO
on the Zolezzi bridge by 31 percent and underestimated by AASHTO on the Old Virginia
bridge by 32percent. The losses predicted by the time-step method using calculated
ultimate coefficients were lower than the extrapolated measured losses on all bridges by
an average of 19 percent. It is recommended to moist cure the bridge for 7 to 10 days
following the stressing to minimize losses (Abstract by authors).